Hubbard Road, Ten Mile Road to Meridian Road

Share Hubbard Road, Ten Mile Road to Meridian Road on Facebook Share Hubbard Road, Ten Mile Road to Meridian Road on Twitter Share Hubbard Road, Ten Mile Road to Meridian Road on Linkedin Email Hubbard Road, Ten Mile Road to Meridian Road link

Starting as early as November, the Ada County Highway District (ACHD) will reconstruct Hubbard Road from Ten Mile Road to Meridian Road as part of the 2025 Arterial & Collector Capital Maintenance Project. Construction is expected to be complete late summer of 2026.*

Project Highlights

  • Reconstructing the roadway pavement on Hubbard Road
  • Upgrading pedestrian ramps, sidewalks, and curb & gutter at key intersections
  • Adding 6-ft bike lanes on both sides of Hubbard Road, with multi-use or asphalt pathways at select locations
  • Replacing an irrigation culvert bridge and the existing pipe on the State Lateral canal
  • Installing railing on top of the Kuna Canal wingwalls
  • Upgrading the City of Kuna’s water and sewer

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

Starting as early as November, the Ada County Highway District (ACHD) will reconstruct Hubbard Road from Ten Mile Road to Meridian Road as part of the 2025 Arterial & Collector Capital Maintenance Project. Construction is expected to be complete late summer of 2026.*

Project Highlights

  • Reconstructing the roadway pavement on Hubbard Road
  • Upgrading pedestrian ramps, sidewalks, and curb & gutter at key intersections
  • Adding 6-ft bike lanes on both sides of Hubbard Road, with multi-use or asphalt pathways at select locations
  • Replacing an irrigation culvert bridge and the existing pipe on the State Lateral canal
  • Installing railing on top of the Kuna Canal wingwalls
  • Upgrading the City of Kuna’s water and sewer

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • December 4, 2025

    Share December 4, 2025 on Facebook Share December 4, 2025 on Twitter Share December 4, 2025 on Linkedin Email December 4, 2025 link
    • Hubbard Road will be closed between Ten Mile Road and Linder Road beginning November 24th.
    • Ten Mile Road and Linder Road will remain open during this phase of work.
    • Roadway has been milled and demo of existing facilities has started.
    • Contractor intends to start City of Kuna utility work next week.
  • November 20, 2025

    Share November 20, 2025 on Facebook Share November 20, 2025 on Twitter Share November 20, 2025 on Linkedin Email November 20, 2025 link
    • Project includes work on Hubbard Road between Ten Mile Road and Meridian Road.
    • Hubbard Road will be closed between Ten Mile Road and Linder Road beginning November 24th.
    • Ten Mile Road and Linder Road will remain open during this phase of work.


  • November 19, 2025 - Detour Map and Information

    Share November 19, 2025 - Detour Map and Information on Facebook Share November 19, 2025 - Detour Map and Information on Twitter Share November 19, 2025 - Detour Map and Information on Linkedin Email November 19, 2025 - Detour Map and Information link


    Work will begin next week on Hubbard Road as part of ACHD's 2025 Arterial and Collector Capital Maintenance project.

    Beginning Monday, Hubbard Road will be closed between Ten Mile and Linder Roads, and the closure is expected to remain in place through the summer of 2026.

    Next year, the intersection of Hubbard and Linder Road will also be closed as part of this work.

    Commuters should use Columbia Road to the north, or Deer Flat Road to the south, to get around the closure during construction (see detour map).

    The work is part of ACHD’s 2025 Arterial & Collector Capital Maintenance Project and includes a full reconstruction of the roadway. When complete, the corridor will feature upgraded pedestrian ramps, new sidewalks, and improved curb and gutter at key intersections, along with other enhancements.



Page last updated: 04 Dec 2025, 03:45 PM