Starting as early as November, the Ada County Highway District (ACHD) will reconstruct Hubbard Road from Ten Mile Road to Meridian Road as part of the 2025 Arterial & Collector Capital Maintenance Project. Construction is expected to be complete late summer of 2026.*
Project Highlights
- Reconstructing the roadway pavement on Hubbard Road
- Upgrading pedestrian ramps, sidewalks, and curb & gutter at key intersections
- Adding 6-ft bike lanes on both sides of Hubbard Road, with multi-use or asphalt pathways at select locations
- Replacing an irrigation culvert bridge and the existing pipe on the State Lateral canal
- Installing railing on top of the Kuna Canal wingwalls
- Upgrading the City of Kuna’s water and sewer
Construction Impacts
- Temporary road closures
- Pedestrian detours and sidewalk closures
- Lane restrictions with flaggers
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
Starting as early as November, the Ada County Highway District (ACHD) will reconstruct Hubbard Road from Ten Mile Road to Meridian Road as part of the 2025 Arterial & Collector Capital Maintenance Project. Construction is expected to be complete late summer of 2026.*
Project Highlights
- Reconstructing the roadway pavement on Hubbard Road
- Upgrading pedestrian ramps, sidewalks, and curb & gutter at key intersections
- Adding 6-ft bike lanes on both sides of Hubbard Road, with multi-use or asphalt pathways at select locations
- Replacing an irrigation culvert bridge and the existing pipe on the State Lateral canal
- Installing railing on top of the Kuna Canal wingwalls
- Upgrading the City of Kuna’s water and sewer
Construction Impacts
- Temporary road closures
- Pedestrian detours and sidewalk closures
- Lane restrictions with flaggers
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
-
May 13, 2026
Share May 13, 2026 on Facebook Share May 13, 2026 on Twitter Share May 13, 2026 on Linkedin Email May 13, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder Road.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
- Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
- Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder Road.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
- Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
- Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th.
-
May 8, 2026
Share May 8, 2026 on Facebook Share May 8, 2026 on Twitter Share May 8, 2026 on Linkedin Email May 8, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder Road.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
- Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
- Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th .
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder Road.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
- Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
- Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th .
-
May 1, 2026
Share May 1, 2026 on Facebook Share May 1, 2026 on Twitter Share May 1, 2026 on Linkedin Email May 1, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
- Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
- Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
-
April 24, 2026
Share April 24, 2026 on Facebook Share April 24, 2026 on Twitter Share April 24, 2026 on Linkedin Email April 24, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
- Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
- Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
-
April 16, 2026
Share April 16, 2026 on Facebook Share April 16, 2026 on Twitter Share April 16, 2026 on Linkedin Email April 16, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is complete.
- Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
- Paving is scheduled for the end of the month, for phase 1.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is complete.
- Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
- Paving is scheduled for the end of the month, for phase 1.
-
April 10, 2026
Share April 10, 2026 on Facebook Share April 10, 2026 on Twitter Share April 10, 2026 on Linkedin Email April 10, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is complete.
- Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
- Paving is scheduled for the end of the month, for phase 1.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is complete.
- Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
- Paving is scheduled for the end of the month, for phase 1.
-
April 2, 2026
Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
-
March 26, 2026
Share March 26, 2026 on Facebook Share March 26, 2026 on Twitter Share March 26, 2026 on Linkedin Email March 26, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation crossings installed. One minor adjustment to a supply pipe complete.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation crossings installed. One minor adjustment to a supply pipe complete.
-
March 19, 2026
Share March 19, 2026 on Facebook Share March 19, 2026 on Twitter Share March 19, 2026 on Linkedin Email March 19, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
-
March 13, 2026
Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 link- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
Page last updated: 13 May 2026, 04:14 PM
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org -
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org
Contact Us
Follow Project
Stay informed
Subscribe for project updates
48 members of your community are following this project