Hubbard Road, Ten Mile Road to Meridian Road

Share Hubbard Road, Ten Mile Road to Meridian Road on Facebook Share Hubbard Road, Ten Mile Road to Meridian Road on Twitter Share Hubbard Road, Ten Mile Road to Meridian Road on Linkedin Email Hubbard Road, Ten Mile Road to Meridian Road link

Starting as early as November, the Ada County Highway District (ACHD) will reconstruct Hubbard Road from Ten Mile Road to Meridian Road as part of the 2025 Arterial & Collector Capital Maintenance Project. Construction is expected to be complete late summer of 2026.*

Project Highlights

  • Reconstructing the roadway pavement on Hubbard Road
  • Upgrading pedestrian ramps, sidewalks, and curb & gutter at key intersections
  • Adding 6-ft bike lanes on both sides of Hubbard Road, with multi-use or asphalt pathways at select locations
  • Replacing an irrigation culvert bridge and the existing pipe on the State Lateral canal
  • Installing railing on top of the Kuna Canal wingwalls
  • Upgrading the City of Kuna’s water and sewer

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

Starting as early as November, the Ada County Highway District (ACHD) will reconstruct Hubbard Road from Ten Mile Road to Meridian Road as part of the 2025 Arterial & Collector Capital Maintenance Project. Construction is expected to be complete late summer of 2026.*

Project Highlights

  • Reconstructing the roadway pavement on Hubbard Road
  • Upgrading pedestrian ramps, sidewalks, and curb & gutter at key intersections
  • Adding 6-ft bike lanes on both sides of Hubbard Road, with multi-use or asphalt pathways at select locations
  • Replacing an irrigation culvert bridge and the existing pipe on the State Lateral canal
  • Installing railing on top of the Kuna Canal wingwalls
  • Upgrading the City of Kuna’s water and sewer

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on Twitter Share June 18, 2026 on Linkedin Email June 18, 2026 link
    • Project includes work on Hubbard Road between Ten Mile Road and Meridian Road.
    • Contractor plans to have extruded curb and lane lines installed by the end of next week. That will make the project substantially complete.
    • Project includes work on Hubbard Road between Ten Mile Road and Meridian Road.
    • Contractor plans to have extruded curb and lane lines installed by the end of next week. That will make the project substantially complete.
  • June 12, 2026

    Share June 12, 2026 on Facebook Share June 12, 2026 on Twitter Share June 12, 2026 on Linkedin Email June 12, 2026 link
    • Hubbard Road between Ten Mile Road and Linder Road is open.
    • Contractor working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) will re-open by the end of the week.
    • Demo of existing roadway is complete.
    • Contractor completed the paving this week.
    • Sewer work for the City of Kuna complete.
    • Waiting on collaring and lane lines. Expected to be completed by next week.
    • Work at the intersection of Linder and Hubbard is complete.
    • Hubbard Road between Ten Mile Road and Linder Road is open.
    • Contractor working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) will re-open by the end of the week.
    • Demo of existing roadway is complete.
    • Contractor completed the paving this week.
    • Sewer work for the City of Kuna complete.
    • Waiting on collaring and lane lines. Expected to be completed by next week.
    • Work at the intersection of Linder and Hubbard is complete.
  • June 5, 2026

    Share June 5, 2026 on Facebook Share June 5, 2026 on Twitter Share June 5, 2026 on Linkedin Email June 5, 2026 link
    • Hubbard Road between Ten Mile Road and Linder Road is open.
    • Contractor working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is closed.
    • Demo of existing roadway is complete.
    • Sewer work for the City of Kuna continues.
    • Work at the intersection of Linder and Hubbard has started. The intersection will remain open under flagging.
    • Paving is scheduled for the week of June 8th.
    • Hubbard Road between Ten Mile Road and Linder Road is open.
    • Contractor working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is closed.
    • Demo of existing roadway is complete.
    • Sewer work for the City of Kuna continues.
    • Work at the intersection of Linder and Hubbard has started. The intersection will remain open under flagging.
    • Paving is scheduled for the week of June 8th.
  • May 29, 2026

    Share May 29, 2026 on Facebook Share May 29, 2026 on Twitter Share May 29, 2026 on Linkedin Email May 29, 2026 link
    • Hubbard Road between Ten Mile Road and Linder Road is open.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is closed.
    • Demo of existing roadway is complete.
    • Sewer work for the City of Kuna continues.
    • Work at the intersection of Linder and Hubbard is expected to start next week.
    • The intersection will remain open under flagging.
    • Paving is scheduled for the week of June 8th.
    • Hubbard Road between Ten Mile Road and Linder Road is open.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is closed.
    • Demo of existing roadway is complete.
    • Sewer work for the City of Kuna continues.
    • Work at the intersection of Linder and Hubbard is expected to start next week.
    • The intersection will remain open under flagging.
    • Paving is scheduled for the week of June 8th.
  • May 21, 2026

    Share May 21, 2026 on Facebook Share May 21, 2026 on Twitter Share May 21, 2026 on Linkedin Email May 21, 2026 link
    • Hubbard Road between Ten Mile Road and Linder Road is open.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is closed.
    • Demo of existing roadway has started.
    • Sewer work for the City of Kuna has started.
    • Hubbard Road between Ten Mile Road and Linder Road is open.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is closed.
    • Demo of existing roadway has started.
    • Sewer work for the City of Kuna has started.
  • May 13, 2026

    Share May 13, 2026 on Facebook Share May 13, 2026 on Twitter Share May 13, 2026 on Linkedin Email May 13, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Contractor completed the City of Kuna utility work, up to Linder Road.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
    • Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Contractor completed the City of Kuna utility work, up to Linder Road.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
    • Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th.
  • May 8, 2026

    Share May 8, 2026 on Facebook Share May 8, 2026 on Twitter Share May 8, 2026 on Linkedin Email May 8, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Contractor completed the City of Kuna utility work, up to Linder Road.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
    • Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th .
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Contractor completed the City of Kuna utility work, up to Linder Road.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
    • Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
    • Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th .
  • May 1, 2026

    Share May 1, 2026 on Facebook Share May 1, 2026 on Twitter Share May 1, 2026 on Linkedin Email May 1, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
    • Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
    • Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
  • April 24, 2026

    Share April 24, 2026 on Facebook Share April 24, 2026 on Twitter Share April 24, 2026 on Linkedin Email April 24, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
    • Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
    • Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
    • Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
  • April 16, 2026

    Share April 16, 2026 on Facebook Share April 16, 2026 on Twitter Share April 16, 2026 on Linkedin Email April 16, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is complete.
    • Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
    • Paving is scheduled for the end of the month, for phase 1.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is complete.
    • Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
    • Paving is scheduled for the end of the month, for phase 1.
Page last updated: 18 Jun 2026, 09:06 AM