April 2, 2026
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
Share April 2, 2026 on Facebook
Share April 2, 2026 on Twitter
Share April 2, 2026 on Linkedin
Email April 2, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends