April 24, 2026
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation work is complete.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Paving started this week, from Ten Mile to Linder, and will continue as weather allows.
- Demo of existing sidewalk, etc. will start next week from Linder to Meridian. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.