February 12, 2026

  • Hubbard Road remains closed between Ten Mile Road and Linder Road.
  • Ten Mile Road and Linder Road will remain open during this phase of work.
  • Flagging and a partial daily closure (east of Linder, on Hubbard) will be complete this week for utility installation within the intersection.
  • Roadway has been milled and demo of existing facilities is ongoing.
  • Contractor to start roadway excavation and grade prep next week at Ten Mile headed east.
  • Contractor continuing the City of Kuna utility work.
  • Contactor has started setting the retaining wall on the northwest end of the project.