- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled and demo of existing facilities is ongoing.
- Contractor started roadway excavation and grade prep this week at Ten Mile headed east.
- Utility conflict was identified, which may delay the excavation on the south side of Hubbard.
- Contractor continuing the City of Kuna utility work.
- Contactor continues setting the retaining wall on the northwest end of the project.