June 12, 2026

  • Hubbard Road between Ten Mile Road and Linder Road is open.
  • Contractor working on concrete sidewalk, curb, and gutter placements at various locations.
  • Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd.
  • Hubbard Road between Linder Road and Meridian Road (SH-69) will re-open by the end of the week.
  • Demo of existing roadway is complete.
  • Contractor completed the paving this week.
  • Sewer work for the City of Kuna complete.
  • Waiting on collaring and lane lines. Expected to be completed by next week.
  • Work at the intersection of Linder and Hubbard is complete.