- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Roadway has been milled, and demo of existing facilities is ongoing.
- Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
- Contractor completed the City of Kuna utility work, up to Linder.
- Contactor has completed the retaining wall on the northwest end of the project.
- Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.