May 8, 2026
- Hubbard Road remains closed between Ten Mile Road and Linder Road.
- Contractor completed the City of Kuna utility work, up to Linder Road.
- Contractor continues working on concrete sidewalk, curb, and gutter placements at various locations.
- Demo of existing sidewalk, etc. is on-going between Linder Rd to Meridian Rd. No traffic disruptions will be implemented until phase 1 (Ten Mile to Linder) is open.
- Hubbard Road between Ten Mile Road and Linder Road is scheduled to re-open May 15th.
- Hubbard Road between Linder Road and Meridian Road (SH-69) is scheduled to be closed May 18th .