August 14, 2026

  • Contactor has completed the milling and paving at select streets around the project.
  • Demo and placement of new sidewalk curb and gutter continues at various locations.
  • Paving at various project locations is scheduled for the end of August.
  • Concrete work along 2nd Street has started this week in anticipation of paving by the end of August.