- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations is scheduled for the end of August.
- Concrete work along 2nd Street is on-going.
- Anticipate paving 2nd Street by the end of August.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations is scheduled for the end of August.
- Concrete work along 2nd Street is on-going.
- Anticipate paving 2nd Street by the end of August.
-
Share August 14, 2026 on Facebook
Share August 14, 2026 on X (formerly Twitter)
Share August 14, 2026 on Linkedin
Email August 14, 2026 link
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations is scheduled for the end of August.
- Concrete work along 2nd Street has started this week in anticipation of paving by the end of August.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations is scheduled for the end of August.
- Concrete work along 2nd Street has started this week in anticipation of paving by the end of August.
-
Share August 7, 2026 on Facebook
Share August 7, 2026 on X (formerly Twitter)
Share August 7, 2026 on Linkedin
Email August 7, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations this week.
- Concrete work along 2nd Street has started this week in anticipation for paving, possibly next week.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations this week.
- Concrete work along 2nd Street has started this week in anticipation for paving, possibly next week.
-
Share July 30, 2026 on Facebook
Share July 30, 2026 on X (formerly Twitter)
Share July 30, 2026 on Linkedin
Email July 30, 2026 link
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base: 1) N Miner Ave. 2) W. Mendi Pl. 3) 2nd Street
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base: 1) N Miner Ave. 2) W. Mendi Pl. 3) 2nd Street
-
Share July 23, 2026 on Facebook
Share July 23, 2026 on X (formerly Twitter)
Share July 23, 2026 on Linkedin
Email July 23, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base: N Miner Ave. W. Mendi Pl. 2 nd Street.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base: N Miner Ave. W. Mendi Pl. 2 nd Street.
-
Share July 17, 2026 on Facebook
Share July 17, 2026 on X (formerly Twitter)
Share July 17, 2026 on Linkedin
Email July 17, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base:
- N Miner Ave.
- W. Mendi Pl.
- 2nd Street
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base:
- N Miner Ave.
- W. Mendi Pl.
- 2nd Street
-
Share July 9, 2026 on Facebook
Share July 9, 2026 on X (formerly Twitter)
Share July 9, 2026 on Linkedin
Email July 9, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base:
- N Miner Ave.
- W. Mendi Pl.
- 2nd Street
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base:
- N Miner Ave.
- W. Mendi Pl.
- 2nd Street
-
Share July 1, 2026 on Facebook
Share July 1, 2026 on X (formerly Twitter)
Share July 1, 2026 on Linkedin
Email July 1, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling is expected to start again next week. Locations: N Miner Ave and W. Mendi Pl.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling is expected to start again next week. Locations: N Miner Ave and W. Mendi Pl.
-
Share June 26, 2026 on Facebook
Share June 26, 2026 on X (formerly Twitter)
Share June 26, 2026 on Linkedin
Email June 26, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
-
Share June 18, 2026 on Facebook
Share June 18, 2026 on X (formerly Twitter)
Share June 18, 2026 on Linkedin
Email June 18, 2026 link
- Road closures continue this week for the milling and paving operations.
- June 18 - Strike Way
- June 19 - Gold Street
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Road closures continue this week for the milling and paving operations.
- June 18 - Strike Way
- June 19 - Gold Street
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.