Kuna Pavement and Pedestrian Improvements 

Share Kuna Pavement and Pedestrian Improvements  on Facebook Share Kuna Pavement and Pedestrian Improvements  on X (formerly Twitter) Share Kuna Pavement and Pedestrian Improvements  on Linkedin Email Kuna Pavement and Pedestrian Improvements  link

The Ada County Highway District (ACHD) will be reconstructing portions of several streets and intersections in Kuna as part of a locally funded project to improve pavement conditions and upgrade the roadway for all users. Work may include reconstructing streets or removing and replacing pavement to enhance roadway conditions, adding bulb-outs where appropriate, filling sidewalk gaps to improve connectivity, and upgrading or installing pedestrian ramps to meet current standards and comply with the Americans with Disabilities Act (ADA).


Pavement reconstruction will occur at the following locations:

  • Trini Drive, Miner Avenue to School Street

  • Miner Avenue, Trini Drive to Gold Street

  • Hayward Avenue, Armand Street to Curtner Street

Pavement reconstruction and pedestrian improvements will occur at the following locations:

  • San Mateo Avenue, Armand Street to Curtner Street (new ADA ramps)

  • Gold Street, Strike Way to School Avenue (bulb-outs, ADA ramps, and driveway Improvements at Gold Street/Pyrite Avenue and Gold Street/Quartzite Avenue intersections)

  • Boise Street, Shady Grove Way to Orchard Avenue (new ADA ramps at Boise Street/Shady Grove Way intersection)

  • Katie Way, Boise Street to Orchard Avenue (new ADA ramps at Katie Way/Boise Street intersection)

  • Ashwood Court, Ash Avenue to east end (new ADA ramps)

  • Orchard Avenue, 4th Street to Boise Street (bulb-outs and ADA ramps at Katie Way/Epson Street intersection)

  • Strike Way, Boise Street to Gold Street (bulb-outs and ADA ramps at Strike Way/Gold Street intersection)

  • Opal Court, Strike Way to cul-de-sac (new ADA ramps at Opal Court/Strike Way intersection)

  • Mendi Place, School Avenue to Goiri Street (ADA ramp upgrades along segment)

When ACHD went out to the public in winter 2023, Orchard Avenue and 4th Street were included in the project. This segment has since been removed.

The Ada County Highway District (ACHD) will be reconstructing portions of several streets and intersections in Kuna as part of a locally funded project to improve pavement conditions and upgrade the roadway for all users. Work may include reconstructing streets or removing and replacing pavement to enhance roadway conditions, adding bulb-outs where appropriate, filling sidewalk gaps to improve connectivity, and upgrading or installing pedestrian ramps to meet current standards and comply with the Americans with Disabilities Act (ADA).


Pavement reconstruction will occur at the following locations:

  • Trini Drive, Miner Avenue to School Street

  • Miner Avenue, Trini Drive to Gold Street

  • Hayward Avenue, Armand Street to Curtner Street

Pavement reconstruction and pedestrian improvements will occur at the following locations:

  • San Mateo Avenue, Armand Street to Curtner Street (new ADA ramps)

  • Gold Street, Strike Way to School Avenue (bulb-outs, ADA ramps, and driveway Improvements at Gold Street/Pyrite Avenue and Gold Street/Quartzite Avenue intersections)

  • Boise Street, Shady Grove Way to Orchard Avenue (new ADA ramps at Boise Street/Shady Grove Way intersection)

  • Katie Way, Boise Street to Orchard Avenue (new ADA ramps at Katie Way/Boise Street intersection)

  • Ashwood Court, Ash Avenue to east end (new ADA ramps)

  • Orchard Avenue, 4th Street to Boise Street (bulb-outs and ADA ramps at Katie Way/Epson Street intersection)

  • Strike Way, Boise Street to Gold Street (bulb-outs and ADA ramps at Strike Way/Gold Street intersection)

  • Opal Court, Strike Way to cul-de-sac (new ADA ramps at Opal Court/Strike Way intersection)

  • Mendi Place, School Avenue to Goiri Street (ADA ramp upgrades along segment)

When ACHD went out to the public in winter 2023, Orchard Avenue and 4th Street were included in the project. This segment has since been removed.

  • August 20, 2026

    Share August 20, 2026 on Facebook Share August 20, 2026 on X (formerly Twitter) Share August 20, 2026 on Linkedin Email August 20, 2026 link
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Paving at various project locations is scheduled for the end of August.
    • Concrete work along 2nd Street is on-going.
    • Anticipate paving 2nd Street by the end of August.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Paving at various project locations is scheduled for the end of August.
    • Concrete work along 2nd Street is on-going.
    • Anticipate paving 2nd Street by the end of August.
  • August 14, 2026

    Share August 14, 2026 on Facebook Share August 14, 2026 on X (formerly Twitter) Share August 14, 2026 on Linkedin Email August 14, 2026 link
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Paving at various project locations is scheduled for the end of August.
    • Concrete work along 2nd Street has started this week in anticipation of paving by the end of August.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Paving at various project locations is scheduled for the end of August.
    • Concrete work along 2nd Street has started this week in anticipation of paving by the end of August.
  • August 7, 2026

    Share August 7, 2026 on Facebook Share August 7, 2026 on X (formerly Twitter) Share August 7, 2026 on Linkedin Email August 7, 2026 link
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Paving at various project locations this week.
    • Concrete work along 2nd Street has started this week in anticipation for paving, possibly next week.
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Paving at various project locations this week.
    • Concrete work along 2nd Street has started this week in anticipation for paving, possibly next week.
  • July 30, 2026

    Share July 30, 2026 on Facebook Share July 30, 2026 on X (formerly Twitter) Share July 30, 2026 on Linkedin Email July 30, 2026 link
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling complete.
    • Locations actively working on excavation and preparation of base: 1) N Miner Ave. 2) W. Mendi Pl. 3) 2nd Street
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling complete.
    • Locations actively working on excavation and preparation of base: 1) N Miner Ave. 2) W. Mendi Pl. 3) 2nd Street
  • July 23, 2026

    Share July 23, 2026 on Facebook Share July 23, 2026 on X (formerly Twitter) Share July 23, 2026 on Linkedin Email July 23, 2026 link
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling complete.
    • Locations actively working on excavation and preparation of base: N Miner Ave. W. Mendi Pl. 2 nd Street.
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling complete.
    • Locations actively working on excavation and preparation of base: N Miner Ave. W. Mendi Pl. 2 nd Street.
  • July 17, 2026

    Share July 17, 2026 on Facebook Share July 17, 2026 on X (formerly Twitter) Share July 17, 2026 on Linkedin Email July 17, 2026 link
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling complete.
    • Locations actively working on excavation and preparation of base:
      • N Miner Ave.
      • W. Mendi Pl.
      • 2nd Street
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling complete.
    • Locations actively working on excavation and preparation of base:
      • N Miner Ave.
      • W. Mendi Pl.
      • 2nd Street
  • July 9, 2026

    Share July 9, 2026 on Facebook Share July 9, 2026 on X (formerly Twitter) Share July 9, 2026 on Linkedin Email July 9, 2026 link
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling complete.
    • Locations actively working on excavation and preparation of base:
      • N Miner Ave.
      • W. Mendi Pl.
      • 2nd Street


    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling complete.
    • Locations actively working on excavation and preparation of base:
      • N Miner Ave.
      • W. Mendi Pl.
      • 2nd Street


  • July 1, 2026

    Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 link
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling is expected to start again next week. Locations: N Miner Ave and W. Mendi Pl.
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Milling is expected to start again next week. Locations: N Miner Ave and W. Mendi Pl.
  • June 26, 2026

    Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 link
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Contactor has completed the milling and paving at select streets around the project.
    • Demo and placement of new sidewalk curb and gutter continues at various locations.
  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 link
    • Road closures continue this week for the milling and paving operations.
      • June 18 - Strike Way
      • June 19 - Gold Street
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
    • Road closures continue this week for the milling and paving operations.
      • June 18 - Strike Way
      • June 19 - Gold Street
    • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
Page last updated: 20 Aug 2026, 03:32 PM