July 1, 2026

  • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
  • Contactor has completed the milling and paving at select streets around the project.
  • Demo and placement of new sidewalk curb and gutter continues at various locations.
  • Milling is expected to start again next week. Locations: N Miner Ave and W. Mendi Pl.