- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base:
- N Miner Ave.
- W. Mendi Pl.
- 2nd Street
Share July 17, 2026 on Facebook
Share July 17, 2026 on X (formerly Twitter)
Share July 17, 2026 on Linkedin
Email July 17, 2026 link
This project is substantially complete.