July 30, 2026
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base: 1) N Miner Ave. 2) W. Mendi Pl. 3) 2nd Street
Share July 30, 2026 on Facebook
Share July 30, 2026 on X (formerly Twitter)
Share July 30, 2026 on Linkedin
Email July 30, 2026 link
This project is substantially complete.