July 30, 2026

  • Contactor has completed the milling and paving at select streets around the project.
  • Demo and placement of new sidewalk curb and gutter continues at various locations.
  • Milling complete.
  • Locations actively working on excavation and preparation of base: 1) N Miner Ave. 2) W. Mendi Pl. 3) 2nd Street