July 9, 2026

  • Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
  • Contactor has completed the milling and paving at select streets around the project.
  • Demo and placement of new sidewalk curb and gutter continues at various locations.
  • Milling complete.
  • Locations actively working on excavation and preparation of base:
    • N Miner Ave.
    • W. Mendi Pl.
    • 2nd Street