October 2, 2026
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations has been completed.
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
- Contractor continues to excavate and import material for the permeable asphalt section on Ashwood. Anticipate paving next week.