August 15, 2025

Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations placed 8/12. Concrete buffer ongoing. Wall starting on northwest corner as early as August 11th.

Lake Hazel to Amity closed for duration of 2nd phase. Milling complete. Utilities relocating services. Removal ongoing. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Concrete fence foundations anticipated starting 8/18.