Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations placed 8/12. Concrete buffer ongoing. Wall starting on northwest corner as early as August 11th.
Lake Hazel to Amity closed for duration of 2nd phase. Milling complete. Utilities relocating services. Removal ongoing. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Concrete fence foundations anticipated starting 8/18.
Share August 8, 2025 on Facebook
Share August 8, 2025 on Linkedin
Email August 8, 2025 link
Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations ongoing. Concrete buffer being placed. Wall starting on northwest corner as early as August 11th.
Lake Hazel to Amity closed for duration of 2nd phase - Milling complete. Utilities relocating services. Removal ongoing. Excavation ongoing. Storm drain ongoing.
Share June 26, 2025 on Facebook
Share June 26, 2025 on Linkedin
Email June 26, 2025 link
- Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opening July 1st in the East/West Direction.
- Conduits and pole foundations being placed.
- Concrete buffer being placed.
- Concrete paving completed until soundwall installed.
- Paving ongoing until June 30th.
- Phase 2 anticipated starting July 1st - Lake Hazel to Amity closed for duration of 2nd phase o Milling Starting July 1st – 3rd.
- Utilities will be relocating services.
Share December 6, 2024 on Facebook
Share December 6, 2024 on Linkedin
Email December 6, 2024 link
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Wall blocks ongoing.
- City of Meridian water ongoing.
- Irrigation will start after City of Meridian water is complete.
Share August 23, 2024 on Facebook
Share August 23, 2024 on Linkedin
Email August 23, 2024 link
Anticipated notice to proceed is mid-September.