Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations placed August 12th. Concrete buffer ongoing. Wall starting on northwest corner in early September. Lake Hazel to Amity closed for duration of 2nd phase. Utilities relocating services. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel.