August 29, 2025

Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction.

  • Conduits and pole foundations placed August 12th.
  • Concrete buffer ongoing.
  • Wall starting on northwest corner in early September.
  • Lake Hazel to Amity closed for duration of 2nd phase.
  • Utilities relocating services.
  • Excavation ongoing.
  • Storm drain ongoing.
  • Sidewalk ongoing between Taconic and Lake Hazel.
  • Working on Taconic intersection.
Share August 29, 2025 on Facebook Share August 29, 2025 on Twitter Share August 29, 2025 on Linkedin Email August 29, 2025 link