December 11, 2025

Eagle and Lake Hazel Intersection

  • Signage and Pavement markings being placed - Weather dependent.
  • Preparing for placement of signal poles.
  • Anticipated December 17th.

Lake Hazel to Amity

  • Lake Hazel to Amity closed for duration.
  • Working on Taconic intersection.
  • Concrete paving ongoing until December 18th.
  • Placements pending weather.