November 20, 2025

  • Eagle and Lake Hazel Intersection o Lake Hazel and Eagle Intersection opened July 1st in the east/west direction.
  • Concrete fence complete.
  • Concrete Intersection being placed: November 21st starting at 2am. November 24th starting at 3 am.
  • Prepping for placement of signal poles. Anticipated December 3rd. Finishing asphalt paving between Lake Hazel and Levine week of November 24th.Lake Hazel to Amity.
  • Lake Hazel to Amity closed for duration.
  • Working on Taconic intersection.
  • Placed concrete paving at all approaches of roundabout o Anticipated paving between Taconic and Amity week of November 10th.
  • Taconic Intersection concrete placement starting November 19th.