September 5, 2025
- Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
- Conduits and pole foundations placed August 12th
- Concrete buffer ongoing
- Wall starting on northwest corner in early September
- Lake Hazel to Amity closed for duration of 2nd phase
- Utilities relocating services
- Excavation ongoing
- Storm drain ongoing
- Sidewalk ongoing between Taconic and Lake Hazel
- Working on Taconic intersection