Liberty Street, Denton to Douglas

Share Liberty Street, Denton to Douglas on Facebook Share Liberty Street, Denton to Douglas on Twitter Share Liberty Street, Denton to Douglas on Linkedin Email Liberty Street, Denton to Douglas link

In November, the Ada County Highway District (ACHD) will begin construction on Liberty Street between Denton Street and Douglas Street. The project includes pavement maintenance as well as safety and connectivity improvements for bicyclists and pedestrians. Work is expected to be complete in fall 2026.*

Project Description

  • Perform pavement maintenance to improve roadway conditions on Liberty Street from Douglas to Denton.
  • Construct curb, gutter, and a multi-use pathway on the east side of Liberty Street from Douglas to Denton.
  • Add sidewalk on the west side of Liberty Street from Douglas to Denton.
  • On-street parking will remain on the west side.
  • Add new pedestrian ramps and bikeway signage where necessary.

Construction Impacts

  • Road closures are expected during construction
  • Traffic lanes will shift as work progresses
  • On-street parking will be reduced during construction
  • Lane restrictions with flaggers will help direct traffic
  • Expect general construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts and maintain access

*Construction schedules may change.

In November, the Ada County Highway District (ACHD) will begin construction on Liberty Street between Denton Street and Douglas Street. The project includes pavement maintenance as well as safety and connectivity improvements for bicyclists and pedestrians. Work is expected to be complete in fall 2026.*

Project Description

  • Perform pavement maintenance to improve roadway conditions on Liberty Street from Douglas to Denton.
  • Construct curb, gutter, and a multi-use pathway on the east side of Liberty Street from Douglas to Denton.
  • Add sidewalk on the west side of Liberty Street from Douglas to Denton.
  • On-street parking will remain on the west side.
  • Add new pedestrian ramps and bikeway signage where necessary.

Construction Impacts

  • Road closures are expected during construction
  • Traffic lanes will shift as work progresses
  • On-street parking will be reduced during construction
  • Lane restrictions with flaggers will help direct traffic
  • Expect general construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts and maintain access

*Construction schedules may change.

  • March 13, 2026

    Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 link
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Seepage beds, City of Boise sewer work, storm sewer pipe and irrigation pipe are on-going.
  • March 6, 2026

    Share March 6, 2026 on Facebook Share March 6, 2026 on Twitter Share March 6, 2026 on Linkedin Email March 6, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Seepage beds, City of Boise sewer work, storm sewer pipe and irrigation pipe are on-going.
  • February 27, 2026

    Share February 27, 2026 on Facebook Share February 27, 2026 on Twitter Share February 27, 2026 on Linkedin Email February 27, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Seepage beds, City of Boise sewer work, storm sewer pipe and irrigation pipe are on-going.
  • February 19, 2026

    Share February 19, 2026 on Facebook Share February 19, 2026 on Twitter Share February 19, 2026 on Linkedin Email February 19, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Seepage beds, City of Boise sewer work, storm sewer pipe and irrigation pipe are on-going.
  • February 12, 2026

    Share February 12, 2026 on Facebook Share February 12, 2026 on Twitter Share February 12, 2026 on Linkedin Email February 12, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Seepage beds, City of Boise sewer work, storm sewer pipe and irrigation pipe are on-going.
  • February 5, 2026

    Share February 5, 2026 on Facebook Share February 5, 2026 on Twitter Share February 5, 2026 on Linkedin Email February 5, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Excavation for seepage beds began January 12th and is on-going.
    • City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
  • January 30, 2026

    Share January 30, 2026 on Facebook Share January 30, 2026 on Twitter Share January 30, 2026 on Linkedin Email January 30, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Excavation for seepage beds began January 12th and is on-going.
    • City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
  • January 23, 2026

    Share January 23, 2026 on Facebook Share January 23, 2026 on Twitter Share January 23, 2026 on Linkedin Email January 23, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Excavation for seepage beds began January 12th and is on-going.
    • City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
  • January 16, 2026

    Share January 16, 2026 on Facebook Share January 16, 2026 on Twitter Share January 16, 2026 on Linkedin Email January 16, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • Excavation for seepage beds began January 12th and is on-going.
    • City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January
  • January 9, 2026

    Share January 9, 2026 on Facebook Share January 9, 2026 on Twitter Share January 9, 2026 on Linkedin Email January 9, 2026 link
    • Utility work started in advance of construction and is on-going.
    • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
    • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
    • The asphalt has been milled off the east side of the road.
    • City of Boise sewer work will begin January 12th, followed by storm sewer pipe and irrigation pipe.
Page last updated: 13 Mar 2026, 01:20 PM