August 14, 2026

  • Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
  • Asphalt paving for Phase 1 on the east side was completed on June 5th.
  • Work on the west side of the roadway began on June 19th.
  • Veolia began replacing the water line on June 23rd. Work is on-going and anticipated to be complete at the end of August.
  • ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th.