January 30, 2026

  • Utility work started in advance of construction and is on-going.
  • Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
  • Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
  • The asphalt has been milled off the east side of the road.
  • Excavation for seepage beds began January 12th and is on-going.
  • City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.