June 5, 2026
- Utility work started in advance of construction and is complete for the first phase of work.
- Liberty Street is closed to northbound traffic between Franklin Road and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Franklin Road and Denton Street.
- Seepage beds, irrigation work, City of Boise sewer work and storm drain pipe are complete for this phase of work.
- Contractor is excavating and placing gravel for the roadway.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 is scheduled for early June.
- Work on the west side of the roadway is scheduled to begin in late June.