May 8, 2026
- Utility work started in advance of construction and is complete for the first phase of work.
- Liberty Street is closed to northbound traffic between Franklin Road. and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Franklin Road and Denton Street.
- Seepage beds, irrigation work, City of Boise sewer work and storm drain pipe are complete for this phase of work.
- Contractor is excavating and placing gravel for the roadway.
- Concrete for curb and gutter started May 7th and is on-going.