November 6, 2026

  • Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
  • Utility work is complete.
  • ACHD’s contractor has been given a Stop Work order effective October 9, 2026.
  • ACHD met with the bonding company on October 13th , October 19th and October 30th.
  • A potential completion contractor has been identified and is under review by the bonding company with a response expected no later than November 6th.
  • The southbound lane will be temporarily paved in late November or early December so the road can be re-opened for the winter.