Liberty Street, Denton to Douglas
In November, the Ada County Highway District (ACHD) will begin construction on Liberty Street between Denton Street and Douglas Street. The project includes pavement maintenance as well as safety and connectivity improvements for bicyclists and pedestrians. Work is expected to be complete in fall 2026.*
Project Description
- Perform pavement maintenance to improve roadway conditions on Liberty Street from Douglas to Denton.
- Construct curb, gutter, and a multi-use pathway on the east side of Liberty Street from Douglas to Denton.
- Add sidewalk on the west side of Liberty Street from Douglas to Denton.
- On-street parking will remain on the west side.
- Add new pedestrian ramps and bikeway signage where necessary.
Construction Impacts
- Road closures are expected during construction
- Traffic lanes will shift as work progresses
- On-street parking will be reduced during construction
- Lane restrictions with flaggers will help direct traffic
- Expect general construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts and maintain access
*Construction schedules may change.
In November, the Ada County Highway District (ACHD) will begin construction on Liberty Street between Denton Street and Douglas Street. The project includes pavement maintenance as well as safety and connectivity improvements for bicyclists and pedestrians. Work is expected to be complete in fall 2026.*
Project Description
- Perform pavement maintenance to improve roadway conditions on Liberty Street from Douglas to Denton.
- Construct curb, gutter, and a multi-use pathway on the east side of Liberty Street from Douglas to Denton.
- Add sidewalk on the west side of Liberty Street from Douglas to Denton.
- On-street parking will remain on the west side.
- Add new pedestrian ramps and bikeway signage where necessary.
Construction Impacts
- Road closures are expected during construction
- Traffic lanes will shift as work progresses
- On-street parking will be reduced during construction
- Lane restrictions with flaggers will help direct traffic
- Expect general construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts and maintain access
*Construction schedules may change.
-
February 5, 2026
Share February 5, 2026 on Facebook Share February 5, 2026 on Twitter Share February 5, 2026 on Linkedin Email February 5, 2026 link- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- Excavation for seepage beds began January 12th and is on-going.
- City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- Excavation for seepage beds began January 12th and is on-going.
- City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
-
January 30, 2026
Share January 30, 2026 on Facebook Share January 30, 2026 on Twitter Share January 30, 2026 on Linkedin Email January 30, 2026 link- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- Excavation for seepage beds began January 12th and is on-going.
- City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- Excavation for seepage beds began January 12th and is on-going.
- City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
-
January 23, 2026
Share January 23, 2026 on Facebook Share January 23, 2026 on Twitter Share January 23, 2026 on Linkedin Email January 23, 2026 link- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- Excavation for seepage beds began January 12th and is on-going.
- City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- Excavation for seepage beds began January 12th and is on-going.
- City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January.
-
January 16, 2026
Share January 16, 2026 on Facebook Share January 16, 2026 on Twitter Share January 16, 2026 on Linkedin Email January 16, 2026 link- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- Excavation for seepage beds began January 12th and is on-going.
- City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January
- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- Excavation for seepage beds began January 12th and is on-going.
- City of Boise sewer work, storm sewer pipe and irrigation pipe will start in late January
-
January 9, 2026
Share January 9, 2026 on Facebook Share January 9, 2026 on Twitter Share January 9, 2026 on Linkedin Email January 9, 2026 link- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- City of Boise sewer work will begin January 12th, followed by storm sewer pipe and irrigation pipe.
- Utility work started in advance of construction and is on-going.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- The asphalt has been milled off the east side of the road.
- City of Boise sewer work will begin January 12th, followed by storm sewer pipe and irrigation pipe.
-
December 18, 2025
Share December 18, 2025 on Facebook Share December 18, 2025 on Twitter Share December 18, 2025 on Linkedin Email December 18, 2025 link- Work began December 16th.
- Utility work started in advance of construction.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- Work began December 16th.
- Utility work started in advance of construction.
- Liberty Street is closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
-
December 11, 2025
Share December 11, 2025 on Facebook Share December 11, 2025 on Twitter Share December 11, 2025 on Linkedin Email December 11, 2025 link- Utility work started in advance of construction.
- Notice to Proceed is anticipated for December 16th.
- Liberty Street will be closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street will be open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
- Utility work started in advance of construction.
- Notice to Proceed is anticipated for December 16th.
- Liberty Street will be closed to northbound traffic between Douglas Street and Denton Street.
- Liberty Street will be open to one-lane, one-way traffic in the southbound direction between Douglas Street and Denton Street.
-
December 4, 2025
Share December 4, 2025 on Facebook Share December 4, 2025 on Twitter Share December 4, 2025 on Linkedin Email December 4, 2025 link- Notice to Proceed is anticipated for mid-December.
- Utility work is starting in advance of construction.
- Notice to Proceed is anticipated for mid-December.
- Utility work is starting in advance of construction.
-
November 14, 2025
Share November 14, 2025 on Facebook Share November 14, 2025 on Twitter Share November 14, 2025 on Linkedin Email November 14, 2025 link- Utility work is starting in advance of construction.
- Utility work is starting in advance of construction.
-
Construction to start November 2025
Share Construction to start November 2025 on Facebook Share Construction to start November 2025 on Twitter Share Construction to start November 2025 on Linkedin Email Construction to start November 2025 linkIn November, the Ada County Highway District (ACHD) will begin construction on Liberty Street from Denton Street to Douglas Street. Work is expected to be complete in fall 2026.*
*Construction schedules may change.
In November, the Ada County Highway District (ACHD) will begin construction on Liberty Street from Denton Street to Douglas Street. Work is expected to be complete in fall 2026.*
*Construction schedules may change.
Follow Project
TImeline
-
2021
Liberty Street, Denton to Douglas has finished this stageDesign started
-
July 2022
Liberty Street, Denton to Douglas has finished this stageGather public input
-
2023
Liberty Street, Denton to Douglas has finished this stageBegin purchasing property necessary for project
-
November 2025
Liberty Street, Denton to Douglas is currently at this stageStart construction
-
Fall 2026
this is an upcoming stage for Liberty Street, Denton to DouglasConstruction is expected to be complete.*
Contact Us
Who's Listening
-
Supervisor, Construction
Phone 208-387-6100 Email connect@achdidaho.org -
Community and Business Relations Coordinator
Phone 208-387-6100 Email connect@achdidaho.org -
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org