August 15, 2025
- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placing pole foundations starting August 18th on South side of Overland.
Share August 15, 2025 on Facebook
Share August 15, 2025 on Twitter
Share August 15, 2025 on Linkedin
Email August 15, 2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends