Linder Overpass and Roadway Project, Franklin to Overland

Share Linder Overpass and Roadway Project, Franklin to Overland on Facebook Share Linder Overpass and Roadway Project, Franklin to Overland on Twitter Share Linder Overpass and Roadway Project, Franklin to Overland on Linkedin Email Linder Overpass and Roadway Project, Franklin to Overland link

The Ada County Highway District (ACHD) is constructing improvements for Linder Road between Franklin Road and Overland Road.

The project includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The project also extends Linder Road from Overland Road to the new overpass.

The Ada County Highway District (ACHD) is constructing improvements for Linder Road between Franklin Road and Overland Road.

The project includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The project also extends Linder Road from Overland Road to the new overpass.

  • Phase 2 Construction to Start this Summer

    Share Phase 2 Construction to Start this Summer on Facebook Share Phase 2 Construction to Start this Summer on Twitter Share Phase 2 Construction to Start this Summer on Linkedin Email Phase 2 Construction to Start this Summer link

    The Ada County Highway District (ACHD), in coordination with the Idaho Transportation Department (ITD) and the City of Meridian, is starting Phase 2 of the Linder Road Overpass and Roadway Project as early as June 2026. Work is expected to be complete in late 2027.*

    *Schedule subject to change.

    Project Description

    • Construct a new 4-lane overpass spanning Interstate 84.
    • Widen Linder Road, between Franklin Road and new overpass to two lanes in each direction with a center turn lane.
    • Extend Linder Road, from Overland Road to new overpass.
    • Add multi-use pathways for pedestrians and bicyclists.

    Construction Impacts

    • Lane Restrictions: Linder Road may have a reduced number of travel lanes occasionally, but flaggers will be present.
    • Utility Work: Substantial utility work is planned for this project and may include water, power and communications, and gas.
    • Pedestrians and Bike Route Detours: Detours will be in place to keep pedestrians and bicyclists moving safely.
    • Construction Activity: Expect general construction noise, including equipment backup alarms, dust and ground vibration.
    • Property Owner Access: Access to businesses and homes will stay open. The contractor will work with property owners to keep entrances clear or provide alternate accesses.

    The Ada County Highway District (ACHD), in coordination with the Idaho Transportation Department (ITD) and the City of Meridian, is starting Phase 2 of the Linder Road Overpass and Roadway Project as early as June 2026. Work is expected to be complete in late 2027.*

    *Schedule subject to change.

    Project Description

    • Construct a new 4-lane overpass spanning Interstate 84.
    • Widen Linder Road, between Franklin Road and new overpass to two lanes in each direction with a center turn lane.
    • Extend Linder Road, from Overland Road to new overpass.
    • Add multi-use pathways for pedestrians and bicyclists.

    Construction Impacts

    • Lane Restrictions: Linder Road may have a reduced number of travel lanes occasionally, but flaggers will be present.
    • Utility Work: Substantial utility work is planned for this project and may include water, power and communications, and gas.
    • Pedestrians and Bike Route Detours: Detours will be in place to keep pedestrians and bicyclists moving safely.
    • Construction Activity: Expect general construction noise, including equipment backup alarms, dust and ground vibration.
    • Property Owner Access: Access to businesses and homes will stay open. The contractor will work with property owners to keep entrances clear or provide alternate accesses.
  • October 31, 2025

    Share October 31, 2025 on Facebook Share October 31, 2025 on Twitter Share October 31, 2025 on Linkedin Email October 31, 2025 link

    Rail ongoing on Linder.

    Rail ongoing on Linder.

  • October 24, 2025

    Share October 24, 2025 on Facebook Share October 24, 2025 on Twitter Share October 24, 2025 on Linkedin Email October 24, 2025 link
    • Anticipated signal turn on October 22nd.
    • Rail ongoing on Linder.
    • Anticipated signal turn on October 22nd.
    • Rail ongoing on Linder.
  • October 17, 2025

    Share October 17, 2025 on Facebook Share October 17, 2025 on Twitter Share October 17, 2025 on Linkedin Email October 17, 2025 link
    • Linder Rd. south side closure began June 12th.
    • Utility Pole removed.
    • Signal pole and mast arms placed.
    • Last if pavement markings on Friday.
    • Pulling fiber in signal.
    • Linder Rd. south side closure began June 12th.
    • Utility Pole removed.
    • Signal pole and mast arms placed.
    • Last if pavement markings on Friday.
    • Pulling fiber in signal.
  • October 10, 2025

    Share October 10, 2025 on Facebook Share October 10, 2025 on Twitter Share October 10, 2025 on Linkedin Email October 10, 2025 link
    • Linder Rd. south side closure began June 12th
    • Sidewalk ongoing
    • Utility company working on moving facilities
    • Project delayed until pole is relocated
    • Anticipated week of the Oct 13th
    • Linder Rd. south side closure began June 12th
    • Sidewalk ongoing
    • Utility company working on moving facilities
    • Project delayed until pole is relocated
    • Anticipated week of the Oct 13th
  • October 2, 2025

    Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 link

    Linder Rd. south side closure began June 12th. Sidewalk ongoing. Utility company working on moving facilities. Project delayed until pole is relocated.

    Linder Rd. south side closure began June 12th. Sidewalk ongoing. Utility company working on moving facilities. Project delayed until pole is relocated.

  • September 26, 2025

    Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link
    • Linder Rd. south side closure began June 12th.
    • Sidewalk ongoing.
    • Utility company working on moving facilities. Project delayed until pole is relocated. Pavement markings ongoing.
    • Linder Rd. south side closure began June 12th.
    • Sidewalk ongoing.
    • Utility company working on moving facilities. Project delayed until pole is relocated. Pavement markings ongoing.
  • September 19, 2025

    Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 link

    Linder Rd. south side closure began June 12th.

    Sidewalk ongoing.

    Utility company working on moving facilities.

    Project delayed until pole is relocated.

    Linder Rd. south side closure began June 12th.

    Sidewalk ongoing.

    Utility company working on moving facilities.

    Project delayed until pole is relocated.

  • September 12, 2025

    Share September 12, 2025 on Facebook Share September 12, 2025 on Twitter Share September 12, 2025 on Linkedin Email September 12, 2025 link
    • Linder Rd. south side closure began June 12th. Sidewalk ongoing. Utility company working on moving facilities. Project delayed until pole is relocated.
    • Linder Rd. south side closure began June 12th. Sidewalk ongoing. Utility company working on moving facilities. Project delayed until pole is relocated.
  • September 5, 2025

    Share September 5, 2025 on Facebook Share September 5, 2025 on Twitter Share September 5, 2025 on Linkedin Email September 5, 2025 link
    • Linder Rd. south side closure began June 12th.
    • Sidewalk ongoing.
    • Idaho Power relocating their utilities.
    • Placed pole foundations.
    • Placing curb and gutter south of Overland.
    • Anticipated paving September 4th.
    • Concrete median after paving anticipated September 10th.
    • Linder Rd. south side closure began June 12th.
    • Sidewalk ongoing.
    • Idaho Power relocating their utilities.
    • Placed pole foundations.
    • Placing curb and gutter south of Overland.
    • Anticipated paving September 4th.
    • Concrete median after paving anticipated September 10th.
Page last updated: 21 May 2026, 04:33 PM