July 18, 2025

  • Linder Rd. south side closure began June 12th and will be in place through late July
  • North side paved
  • Sidewalk ongoing
  • Excavating south side
  • Idaho Power relocating their utilities
  • Storm drain ongoing
Share July 18, 2025 on Facebook Share July 18, 2025 on Twitter Share July 18, 2025 on Linkedin Email July 18, 2025 link