June 13, 2025

  • Irrigation complete.
  • Retaining wall ongoing.
  • Pole bases being placed.
  • Linder Rd. south side closure began June 12th and will be in place through late July.
Share June 13, 2025 on Facebook Share June 13, 2025 on X (formerly Twitter) Share June 13, 2025 on Linkedin Email June 13, 2025 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>