June 26, 2025

  • Irrigation Complete.
  • Retaining wall complete.
  • Pole bases being placed.
  • Linder Rd. south side closure began June 12th and will be in place through late July.
  • Curb being placed on north side of project.
  • Removals ongoing on south side of project.