Linder Overpass and Roadway Project, Franklin to Overland

Share Linder Overpass and Roadway Project, Franklin to Overland on Facebook Share Linder Overpass and Roadway Project, Franklin to Overland on Twitter Share Linder Overpass and Roadway Project, Franklin to Overland on Linkedin Email Linder Overpass and Roadway Project, Franklin to Overland link

The Ada County Highway District (ACHD) is designing future improvements for Linder Road between Franklin Road and Overland Road.

The proposed design includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The design also proposes extending Linder Road from Overland Road to the new overpass.

The Ada County Highway District (ACHD) is designing future improvements for Linder Road between Franklin Road and Overland Road.

The proposed design includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The design also proposes extending Linder Road from Overland Road to the new overpass.

  • June 6, 2025

    06 Jun 2025
    Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link
    • Irrigation complete.
    • Retaining wall ongoing.
    • Pole bases being placed.
    • Linder Rd. south side anticipated closure beginning June 16th.
  • May 30, 2025

    30 May 2025
    Share May 30, 2025 on Facebook Share May 30, 2025 on Twitter Share May 30, 2025 on Linkedin Email May 30, 2025 link
    • Irrigation complete.
    • Retaining wall ongoing.
    • Utility work ongoing.
  • May 23, 2025

    23 May 2025
    Share May 23, 2025 on Facebook Share May 23, 2025 on Twitter Share May 23, 2025 on Linkedin Email May 23, 2025 link
    • Irrigation complete.
    • Retaining wall ongoing.
  • May 16, 2025

    16 May 2025
    Share May 16, 2025 on Facebook Share May 16, 2025 on Twitter Share May 16, 2025 on Linkedin Email May 16, 2025 link
    • Irrigation complete.
    • Retaining wall ongoing.
  • May 8, 2025

    08 May 2025
    Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link
    • Irrigation complete.
    • Storm drain being installed.
    • Excavating and prepping for wall on Linder.
    • Retaining wall ongoing.
  • May 2, 2025

    02 May 2025
    Share May 2, 2025 on Facebook Share May 2, 2025 on Twitter Share May 2, 2025 on Linkedin Email May 2, 2025 link
    • Irrigation Complete.
    • Storm drain being installed.
    • Excavating and prepping for wall on Linder.
  • April 25, 2025

    25 Apr 2025
    Share April 25, 2025 on Facebook Share April 25, 2025 on Twitter Share April 25, 2025 on Linkedin Email April 25, 2025 link
    • Irrigation complete.
    • Storm drain being installed.
    • Excavating and prepping for wall on Linder.
  • April 11, 2025

    11 Apr 2025
    Share April 11, 2025 on Facebook Share April 11, 2025 on Twitter Share April 11, 2025 on Linkedin Email April 11, 2025 link
    • Irrigation started on southwest corner.
  • April 4, 2025

    04 Apr 2025
    Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 link
    • Notice to proceed is anticipated for April 7th.
    • Starting irrigation on southwest corner.
  • March 19, 2025

    19 Mar 2025
    Share March 19, 2025 on Facebook Share March 19, 2025 on Twitter Share March 19, 2025 on Linkedin Email March 19, 2025 link

    Idaho Materials and Construction is set to begin construction on Phase 1 of the Linder Rd, Overland Rd to Franklin Rd project on March 24th, 2025.

    Construction is scheduled to be finished by late September 2025.

    This phase of the project consists of constructing the new north leg of the Overland Rd and Linder Rd Intersection, a large retaining wall for the new north leg, updating the signals to change from a three way to a four way intersection, installing 10’ multi-use pathways to complete connectivity through the intersection, and adding bike ramps at the intersection to transition cyclists off of the road and onto the multi-use pathway. The south leg will be closed from just north of Spanish Sun Way to Overland Rd during the second half of the project. Detours will be provided, and temporary traffic calming measures will be implemented in adjacent neighborhoods to address cut-through traffic. Phase 2 of the project, which includes the new overpass and road widening on Linder Rd from I-84 to Franklin Rd, is scheduled to begin in the summer of 2026.