April 2, 2026

  • Linder Road will be closed November 18th through mid-May 2026.
  • Linder Rd - Excavation ongoing. Light bases set. Preparing for sidewalk. Sidewalk being placed. Finishing up irrigation ditches.
  • Foothills Bridge - Diversion wall complete. Backfilling structure. Rail remaining.
  • Dry Creek Bridge - East side complete. Backfilling ongoing. Wall ongoing. Cut off wall remaining.
  • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.