Share February 27, 2026 on Facebook
Share February 27, 2026 on Linkedin
Email February 27, 2026 link
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
- Foothills Bridge - Dewatering setup. Deck placed February 19th. Diversion wall ongoing.
- Dry Creek Bridge - East side complete. Shoe fly being installed to allow access to east side. Starting west side. Footings ongoing.
- Utilities: Relocations continuing for: Idaho Power - complete. Intermountain Gas – ongoing. Veolia – up to Briar Rock. Fiber utilities - ongoing.
Share February 19, 2026 on Facebook
Share February 19, 2026 on Linkedin
Email February 19, 2026 link
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
- Foothills Bridge - Dewatering setup. Deck placed February 19th.
- Dry Creek Bridge - East side complete. Shoe fly being installed to allow access to east side. Starting west side.
- Utilities - Relocations continuing for: Idaho Power - complete. Intermountain Gas – ongoing. Veolia – ongoing. Fiber utilities - ongoing.
Share February 12, 2026 on Facebook
Share February 12, 2026 on Linkedin
Email February 12, 2026 link
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
- Foothills Bridge - Dewatering setup. Footings placed. South wall placed. Working on north wall. Diversion structure walls placed. Working on deck.
- Dry Creek Bridge - East side complete. Shoe fly being installed to allow access to east side. Starting west side.
- Utilities - Relocations continuing for: Idaho Power - complete. Intermountain Gas – ongoing. Veolia – ongoing. Fiber utilities.
Share February 5, 2026 on Facebook
Share February 5, 2026 on Linkedin
Email February 5, 2026 link
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
- Foothills Bridge - Bridge removed. Dewatering setup. Footings placed. South wall placed. Working on north wall. Diversion structure walls placed.
- Dry Creek Bridge- East side complete. Shoe fly being installed to allow access to West side.
- Utilities - Relocations continuing for: Idaho Power - complete. Intermountain Gas – ongoing. Veolia – ongoing. Fiber utilities.
Share January 30, 2026 on Facebook
Share January 30, 2026 on Linkedin
Email January 30, 2026 link
- Utility work started in advance of construction and is on-going.
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Foothills Bridge: Bridge removed. Dewatering setup. Footings placed. South wall placed. Working on north wall.
- Dry Creek Bridge: Precast being fabricated. Starting on east side for installation. Headwall being formed.
- Utilities: Relocations continuing for: Idaho Power - complete. Intermountain Gas, Veolia – ongoing. Fiber utilities.
Share January 23, 2026 on Facebook
Share January 23, 2026 on Linkedin
Email January 23, 2026 link
- Utility work started in advance of construction and is on-going.
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Foothills Bridge - Bridge removed. Dewatering setup. Footings placed. South wall placed. Working on north wall.
- Dry Creek Bridge - Precast being fabricated. Starting on east side for installation. Headwall being formed.
- Utilities - Relocations continuing for: Idaho Power - complete. Intermountain Gas, Veolia – ongoing and Fiber utilities.
Share January 16, 2026 on Facebook
Share January 16, 2026 on Linkedin
Email January 16, 2026 link
- Utility work started in advance of construction and is on-going.
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
Foothills Bridge
- Bridge removed.
- Dewatering setup.
- Footings placed.
Dry Creek Bridge
- Precast being fabricated.
- Starting on east side for installation.
Utilities
Relocating continuing for: Idaho Power, Intermountain Gas, Veolia
Share January 9, 2025 on Facebook
Share January 9, 2025 on Linkedin
Email January 9, 2025 link
- Utility work started in advance of construction and is on-going.
- Speed calming measures installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Foothills Bridge - Bridge removed. Dewatering setup. Footings placed.
- Dry Creek Bridge - Precast being fabricated. Starting on east side for installation.
- Utilities - Relocation continuing for: Idaho Power, Intermountain Gas & Veolia.
Share December 18, 2025 on Facebook
Share December 18, 2025 on Linkedin
Email December 18, 2025 link
- Utility work started in advance of construction and is on-going.
- Speed calming measures installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Foothills Bridge - Bridge removed. Dewatering setup. Excavating for footings - Ongoing.
- Dry Creek Bridge - Precast being fabricated.
- Utilities - Relocating continuing for: Idaho Power, Intermountain Gas and Veolia.
Share December 11, 2025 on Facebook
Share December 11, 2025 on Linkedin
Email December 11, 2025 link
- Utility work started in advance of construction and is on-going.
- Speed calming measures installed.
- Linder Road will be closed November 18th through mid-March 2026.
Foothills Bridge
- Bridge removed.
- Dewatering setup.
- Excavating for footings.
Dry Creek Bridge
- Precast being fabricated.
Utilities
- Relocating continuing for: Idaho Power, Intermountain Gas and Veolia.