Linder Road, State Highway 44 to Floating Feather
The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*
Project Description
Roadway
- Widening Linder Road to two lanes in each direction, with a center turn lane.
- Adding landscaped medians where appropriate.
- Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
- Retaining the existing signalized pedestrian crossing at Saguaro Dr.
- Installing roadway lighting along Linder Road
- Constructing bioretention swales to manage roadway drainage.
- Reconstructing two separate bridges on Linder.
Linder and Floating Feather Intersection
- Constructing a roundabout at the Linder and Floating Feather intersection.
- The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
- Adding curb, gutter and a detached multi-use pathway with bike ramps.
- Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
- A truck apron for larger vehicles to use if necessary.
- Constructing a stormwater basin to manage water drainage from the intersection.
*****Linder Road to open May 2026
*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.
The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*
Project Description
Roadway
- Widening Linder Road to two lanes in each direction, with a center turn lane.
- Adding landscaped medians where appropriate.
- Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
- Retaining the existing signalized pedestrian crossing at Saguaro Dr.
- Installing roadway lighting along Linder Road
- Constructing bioretention swales to manage roadway drainage.
- Reconstructing two separate bridges on Linder.
Linder and Floating Feather Intersection
- Constructing a roundabout at the Linder and Floating Feather intersection.
- The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
- Adding curb, gutter and a detached multi-use pathway with bike ramps.
- Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
- A truck apron for larger vehicles to use if necessary.
- Constructing a stormwater basin to manage water drainage from the intersection.
*****Linder Road to open May 2026
*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.
-
May 29, 2026
Share May 29, 2026 on Facebook Share May 29, 2026 on Twitter Share May 29, 2026 on Linkedin Email May 29, 2026 linkEast side of Linder Rd - Sidewalk remaining. Block wall installation ongoing.
West side of Linder Rd - Excavation and concrete removal. Storm drain ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia is working on the new water line. The intersection closure started May 18th. Utilities are relocating facilities.
East side of Linder Rd - Sidewalk remaining. Block wall installation ongoing.
West side of Linder Rd - Excavation and concrete removal. Storm drain ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia is working on the new water line. The intersection closure started May 18th. Utilities are relocating facilities.
-
May 21, 2026
Share May 21, 2026 on Facebook Share May 21, 2026 on Twitter Share May 21, 2026 on Linkedin Email May 21, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block Wall started April 20th.
West side of Linder Rd
- Milling ongoing until May 20th.
- Excavation and concrete removal after milling.
Foothills Bridge
- Rail remaining
Dry Creek Bridge - Complete
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.
- Utilities relocating facilities.
East side of Linder Rd
- Sidewalk remaining.
- Block Wall started April 20th.
West side of Linder Rd
- Milling ongoing until May 20th.
- Excavation and concrete removal after milling.
Foothills Bridge
- Rail remaining
Dry Creek Bridge - Complete
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.
- Utilities relocating facilities.
-
TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday
Share TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday on Facebook Share TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday on Twitter Share TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday on Linkedin Email TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday link
EAGLE — Beginning Monday, May 18, the intersection of Linder Road and Floating Feather Road will be closed for construction of a new roundabout. Commuters should use Palmer Lane or Park Lane for north-south travel, and Beacon Light Road or State Highway 44 for east-west travel (see detour map).
The intersection is expected to remain closed through late 2026.
EAGLE — Beginning Monday, May 18, the intersection of Linder Road and Floating Feather Road will be closed for construction of a new roundabout. Commuters should use Palmer Lane or Park Lane for north-south travel, and Beacon Light Road or State Highway 44 for east-west travel (see detour map).
The intersection is expected to remain closed through late 2026.
-
May 13, 2026
Share May 13, 2026 on Facebook Share May 13, 2026 on Twitter Share May 13, 2026 on Linkedin Email May 13, 2026 linkLinder Rd
- Sidewalk being placed.
- Curb & gutter ongoing.
- Block wall started April 20th.
- Paving anticipated the week of May 11th.
- Paving on the 16th in middle section at SH-44 for 2nd phase signal configuration.
- Traffic signal switch 17th.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.
Linder Rd
- Sidewalk being placed.
- Curb & gutter ongoing.
- Block wall started April 20th.
- Paving anticipated the week of May 11th.
- Paving on the 16th in middle section at SH-44 for 2nd phase signal configuration.
- Traffic signal switch 17th.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.
-
May 12, 2026 - Detour Map Phase II
Share May 12, 2026 - Detour Map Phase II on Facebook Share May 12, 2026 - Detour Map Phase II on Twitter Share May 12, 2026 - Detour Map Phase II on Linkedin Email May 12, 2026 - Detour Map Phase II linkBeginning Monday, May 18, the intersection of Linder Road and Floating Feather Road will be closed for construction of a new roundabout. Commuters should use Palmer Lane or Park Lane as a detour (see detour map).
The intersection is expected to remain closed through late 2026.
The work is part of ACHD's Linder Road, State Highway 44 to Floating Feather Road Project. Work includes a roundabout at the Linder and Floating Feather intersection, with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs) at each leg of the intersection. The project also includes widening Linder Road to two lanes in each direction with a center turn lane, and adding a multi-use pathway along both sides of the roadway, among other improvements.

Beginning Monday, May 18, the intersection of Linder Road and Floating Feather Road will be closed for construction of a new roundabout. Commuters should use Palmer Lane or Park Lane as a detour (see detour map).
The intersection is expected to remain closed through late 2026.
The work is part of ACHD's Linder Road, State Highway 44 to Floating Feather Road Project. Work includes a roundabout at the Linder and Floating Feather intersection, with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs) at each leg of the intersection. The project also includes widening Linder Road to two lanes in each direction with a center turn lane, and adding a multi-use pathway along both sides of the roadway, among other improvements.

-
May 8, 2026
Share May 8, 2026 on Facebook Share May 8, 2026 on Twitter Share May 8, 2026 on Linkedin Email May 8, 2026 linkLinder Road will be closed November 18th through mid-May 2026.
Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & gutter ongoing. Signals removed. Block Wall started April 20th. Paving anticipated the week of May 11th.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on new water line.
Linder Road will be closed November 18th through mid-May 2026.
Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & gutter ongoing. Signals removed. Block Wall started April 20th. Paving anticipated the week of May 11th.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on new water line.
-
May 1, 2026
Share May 1, 2026 on Facebook Share May 1, 2026 on Twitter Share May 1, 2026 on Linkedin Email May 1, 2026 link- Linder Road will be closed November 18th through mid-May 2026.
- Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up Irrigation ditches. Signals removed. Block wall started April 20th.
- Foothills Bridge - Rail remaining.
- Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
- Floating Feather and Linder Roundabout - Veolia working on the new water line.
- Linder Road will be closed November 18th through mid-May 2026.
- Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up Irrigation ditches. Signals removed. Block wall started April 20th.
- Foothills Bridge - Rail remaining.
- Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
- Floating Feather and Linder Roundabout - Veolia working on the new water line.
-
April 24, 2026
Share April 24, 2026 on Facebook Share April 24, 2026 on Twitter Share April 24, 2026 on Linkedin Email April 24, 2026 link- Linder Road will be closed November 18th through mid-May 2026.
- Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up irrigation ditches. Signals removed. Block Wall starting April 20th.
- Foothills Bridge - Rail remaining.
- Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
- Linder Road will be closed November 18th through mid-May 2026.
- Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up irrigation ditches. Signals removed. Block Wall starting April 20th.
- Foothills Bridge - Rail remaining.
- Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
-
April 16, 2026
Share April 16, 2026 on Facebook Share April 16, 2026 on Twitter Share April 16, 2026 on Linkedin Email April 16, 2026 link- Linder Road will be closed November 18th through mid-May 2026.
- Linder Rd - Excavation ongoing. Light bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up irrigation ditches. Signals removed. Block wall starting April 20th.
- Foothills Bridge - Rail remaining.
- Dry Creek Bridge - Complete. Backfill ongoing.
- Linder Road will be closed November 18th through mid-May 2026.
- Linder Rd - Excavation ongoing. Light bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up irrigation ditches. Signals removed. Block wall starting April 20th.
- Foothills Bridge - Rail remaining.
- Dry Creek Bridge - Complete. Backfill ongoing.
-
April 10, 2026
Share April 10, 2026 on Facebook Share April 10, 2026 on Twitter Share April 10, 2026 on Linkedin Email April 10, 2026 linkLinder Rd
- Excavation ongoing.
- Lights bases set.
- Preparing for sidewalk.
- Sidewalk being placed.
- Curb & Gutter ongoing.
- Finishing up Irrigation ditches.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
- Backfill beginning.
Utilities: At Floating Feather
- Veolia - ongoing.
- Fiber utilities - ongoing.
Linder Rd
- Excavation ongoing.
- Lights bases set.
- Preparing for sidewalk.
- Sidewalk being placed.
- Curb & Gutter ongoing.
- Finishing up Irrigation ditches.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
- Backfill beginning.
Utilities: At Floating Feather
- Veolia - ongoing.
- Fiber utilities - ongoing.
Drone Footage
Follow Project
Traffic and Construction Impacts
- Road closures are expected during construction
- Lane restrictions and shifts with flaggers to direct traffic
- Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts and maintain access
Who's Listening
-
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org