Linder Road, State Highway 44 to Floating Feather
The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*
Project Description
Roadway
- Widening Linder Road to two lanes in each direction, with a center turn lane.
- Adding landscaped medians where appropriate.
- Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
- Retaining the existing signalized pedestrian crossing at Saguaro Dr.
- Installing roadway lighting along Linder Road
- Constructing bioretention swales to manage roadway drainage.
- Reconstructing two separate bridges on Linder.
Linder and Floating Feather Intersection
- Constructing a roundabout at the Linder and Floating Feather intersection.
- The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
- Adding curb, gutter and a detached multi-use pathway with bike ramps.
- Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
- A truck apron for larger vehicles to use if necessary.
- Constructing a stormwater basin to manage water drainage from the intersection.
*****Linder Road to open May 2026
*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.
The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*
Project Description
Roadway
- Widening Linder Road to two lanes in each direction, with a center turn lane.
- Adding landscaped medians where appropriate.
- Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
- Retaining the existing signalized pedestrian crossing at Saguaro Dr.
- Installing roadway lighting along Linder Road
- Constructing bioretention swales to manage roadway drainage.
- Reconstructing two separate bridges on Linder.
Linder and Floating Feather Intersection
- Constructing a roundabout at the Linder and Floating Feather intersection.
- The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
- Adding curb, gutter and a detached multi-use pathway with bike ramps.
- Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
- A truck apron for larger vehicles to use if necessary.
- Constructing a stormwater basin to manage water drainage from the intersection.
*****Linder Road to open May 2026
*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.
-
July 9, 2026
Share July 9, 2026 on Facebook Share July 9, 2026 on X (formerly Twitter) Share July 9, 2026 on Linkedin Email July 9, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading the road.
East side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading the road.
-
July 1, 2026
Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.
East side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.
-
June 26, 2026
Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.
East side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.
-
June 18, 2026
Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block wall construction ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain installation ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail installation remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.
East side of Linder Rd
- Sidewalk remaining.
- Block wall construction ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain installation ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail installation remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.
-
June 12, 2026
Share June 12, 2026 on Facebook Share June 12, 2026 on X (formerly Twitter) Share June 12, 2026 on Linkedin Email June 12, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on the new water line. Intersection closure started May 18th. Utilities relocating facilities.
East side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal.
- Storm drain ongoing.
- Pole bases and conduits being placed.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia working on the new water line. Intersection closure started May 18th. Utilities relocating facilities.
-
June 5, 2026
Share June 5, 2026 on Facebook Share June 5, 2026 on X (formerly Twitter) Share June 5, 2026 on Linkedin Email June 5, 2026 linkEast side of Linder Rd
- Sidewalk remaining. Installation of block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal. Storm drain ongoing.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Intersection closure started May 18th.
- Utilities relocating facilities.
East side of Linder Rd
- Sidewalk remaining. Installation of block wall ongoing.
West side of Linder Rd
- Excavation and concrete removal. Storm drain ongoing.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Intersection closure started May 18th.
- Utilities relocating facilities.
-
May 29, 2026
Share May 29, 2026 on Facebook Share May 29, 2026 on X (formerly Twitter) Share May 29, 2026 on Linkedin Email May 29, 2026 linkEast side of Linder Rd - Sidewalk remaining. Block wall installation ongoing.
West side of Linder Rd - Excavation and concrete removal. Storm drain ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia is working on the new water line. The intersection closure started May 18th. Utilities are relocating facilities.
East side of Linder Rd - Sidewalk remaining. Block wall installation ongoing.
West side of Linder Rd - Excavation and concrete removal. Storm drain ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia is working on the new water line. The intersection closure started May 18th. Utilities are relocating facilities.
-
May 21, 2026
Share May 21, 2026 on Facebook Share May 21, 2026 on X (formerly Twitter) Share May 21, 2026 on Linkedin Email May 21, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block Wall started April 20th.
West side of Linder Rd
- Milling ongoing until May 20th.
- Excavation and concrete removal after milling.
Foothills Bridge
- Rail remaining
Dry Creek Bridge - Complete
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.
- Utilities relocating facilities.
East side of Linder Rd
- Sidewalk remaining.
- Block Wall started April 20th.
West side of Linder Rd
- Milling ongoing until May 20th.
- Excavation and concrete removal after milling.
Foothills Bridge
- Rail remaining
Dry Creek Bridge - Complete
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.
- Utilities relocating facilities.
-
TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday
Share TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday on Facebook Share TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday on X (formerly Twitter) Share TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday on Linkedin Email TRAFFIC ADVISORY: Linder & Floating Feather Intersection Closing for Roundabout Construction Monday link
EAGLE — Beginning Monday, May 18, the intersection of Linder Road and Floating Feather Road will be closed for construction of a new roundabout. Commuters should use Palmer Lane or Park Lane for north-south travel, and Beacon Light Road or State Highway 44 for east-west travel (see detour map).
The intersection is expected to remain closed through late 2026.
EAGLE — Beginning Monday, May 18, the intersection of Linder Road and Floating Feather Road will be closed for construction of a new roundabout. Commuters should use Palmer Lane or Park Lane for north-south travel, and Beacon Light Road or State Highway 44 for east-west travel (see detour map).
The intersection is expected to remain closed through late 2026.
-
May 13, 2026
Share May 13, 2026 on Facebook Share May 13, 2026 on X (formerly Twitter) Share May 13, 2026 on Linkedin Email May 13, 2026 linkLinder Rd
- Sidewalk being placed.
- Curb & gutter ongoing.
- Block wall started April 20th.
- Paving anticipated the week of May 11th.
- Paving on the 16th in middle section at SH-44 for 2nd phase signal configuration.
- Traffic signal switch 17th.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.
Linder Rd
- Sidewalk being placed.
- Curb & gutter ongoing.
- Block wall started April 20th.
- Paving anticipated the week of May 11th.
- Paving on the 16th in middle section at SH-44 for 2nd phase signal configuration.
- Traffic signal switch 17th.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.
Drone Footage
Follow Project
Traffic and Construction Impacts
- Road closures are expected during construction
- Lane restrictions and shifts with flaggers to direct traffic
- Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts and maintain access
Who's Listening
-
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org





