Linder Road, State Highway 44 to Floating Feather

Share Linder Road, State Highway 44 to Floating Feather on Facebook Share Linder Road, State Highway 44 to Floating Feather on Twitter Share Linder Road, State Highway 44 to Floating Feather on Linkedin Email Linder Road, State Highway 44 to Floating Feather link

The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*

Project Description

Roadway

  • Widening Linder Road to two lanes in each direction, with a center turn lane.
  • Adding landscaped medians where appropriate.
  • Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
  • Retaining the existing signalized pedestrian crossing at Saguaro Dr.
  • Installing roadway lighting along Linder Road
  • Constructing bioretention swales to manage roadway drainage.
  • Reconstructing two separate bridges on Linder.

Linder and Floating Feather Intersection

  • Constructing a roundabout at the Linder and Floating Feather intersection.
    • The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
  • Adding curb, gutter and a detached multi-use pathway with bike ramps.
  • Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
  • A truck apron for larger vehicles to use if necessary.
  • Constructing a stormwater basin to manage water drainage from the intersection.

*****Linder Road to open May 2026

*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.

The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*

Project Description

Roadway

  • Widening Linder Road to two lanes in each direction, with a center turn lane.
  • Adding landscaped medians where appropriate.
  • Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
  • Retaining the existing signalized pedestrian crossing at Saguaro Dr.
  • Installing roadway lighting along Linder Road
  • Constructing bioretention swales to manage roadway drainage.
  • Reconstructing two separate bridges on Linder.

Linder and Floating Feather Intersection

  • Constructing a roundabout at the Linder and Floating Feather intersection.
    • The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
  • Adding curb, gutter and a detached multi-use pathway with bike ramps.
  • Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
  • A truck apron for larger vehicles to use if necessary.
  • Constructing a stormwater basin to manage water drainage from the intersection.

*****Linder Road to open May 2026

*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.

  • May 8, 2026

    Share May 8, 2026 on Facebook Share May 8, 2026 on Twitter Share May 8, 2026 on Linkedin Email May 8, 2026 link

    Linder Road will be closed November 18th through mid-May 2026.

    Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & gutter ongoing. Signals removed. Block Wall started April 20th. Paving anticipated the week of May 11th.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on new water line.

    Linder Road will be closed November 18th through mid-May 2026.

    Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & gutter ongoing. Signals removed. Block Wall started April 20th. Paving anticipated the week of May 11th.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on new water line.

  • May 1, 2026

    Share May 1, 2026 on Facebook Share May 1, 2026 on Twitter Share May 1, 2026 on Linkedin Email May 1, 2026 link
    • Linder Road will be closed November 18th through mid-May 2026.
    • Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up Irrigation ditches. Signals removed. Block wall started April 20th.
    • Foothills Bridge - Rail remaining.
    • Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
    • Floating Feather and Linder Roundabout - Veolia working on the new water line.
    • Linder Road will be closed November 18th through mid-May 2026.
    • Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up Irrigation ditches. Signals removed. Block wall started April 20th.
    • Foothills Bridge - Rail remaining.
    • Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
    • Floating Feather and Linder Roundabout - Veolia working on the new water line.
  • April 24, 2026

    Share April 24, 2026 on Facebook Share April 24, 2026 on Twitter Share April 24, 2026 on Linkedin Email April 24, 2026 link
    • Linder Road will be closed November 18th through mid-May 2026.
    • Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up irrigation ditches. Signals removed. Block Wall starting April 20th.
    • Foothills Bridge - Rail remaining.
    • Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
    • Linder Road will be closed November 18th through mid-May 2026.
    • Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up irrigation ditches. Signals removed. Block Wall starting April 20th.
    • Foothills Bridge - Rail remaining.
    • Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
  • April 16, 2026

    Share April 16, 2026 on Facebook Share April 16, 2026 on Twitter Share April 16, 2026 on Linkedin Email April 16, 2026 link
    • Linder Road will be closed November 18th through mid-May 2026.
    • Linder Rd - Excavation ongoing. Light bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up irrigation ditches. Signals removed. Block wall starting April 20th.
    • Foothills Bridge - Rail remaining.
    • Dry Creek Bridge - Complete. Backfill ongoing.
    • Linder Road will be closed November 18th through mid-May 2026.
    • Linder Rd - Excavation ongoing. Light bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up irrigation ditches. Signals removed. Block wall starting April 20th.
    • Foothills Bridge - Rail remaining.
    • Dry Creek Bridge - Complete. Backfill ongoing.
  • April 10, 2026

    Share April 10, 2026 on Facebook Share April 10, 2026 on Twitter Share April 10, 2026 on Linkedin Email April 10, 2026 link

    Linder Rd

    • Excavation ongoing.
    • Lights bases set.
    • Preparing for sidewalk.
    • Sidewalk being placed.
    • Curb & Gutter ongoing.
    • Finishing up Irrigation ditches.

    Foothills Bridge

    • Rail remaining.

    Dry Creek Bridge

    • Complete.
    • Backfill beginning.

    Utilities: At Floating Feather

    • Veolia - ongoing.
    • Fiber utilities - ongoing.

    Linder Rd

    • Excavation ongoing.
    • Lights bases set.
    • Preparing for sidewalk.
    • Sidewalk being placed.
    • Curb & Gutter ongoing.
    • Finishing up Irrigation ditches.

    Foothills Bridge

    • Rail remaining.

    Dry Creek Bridge

    • Complete.
    • Backfill beginning.

    Utilities: At Floating Feather

    • Veolia - ongoing.
    • Fiber utilities - ongoing.
  • April 2, 2026

    Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 link
    • Linder Road will be closed November 18th through mid-May 2026.
    • Linder Rd - Excavation ongoing. Light bases set. Preparing for sidewalk. Sidewalk being placed. Finishing up irrigation ditches.
    • Foothills Bridge - Diversion wall complete. Backfilling structure. Rail remaining.
    • Dry Creek Bridge - East side complete. Backfilling ongoing. Wall ongoing. Cut off wall remaining.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
    • Linder Road will be closed November 18th through mid-May 2026.
    • Linder Rd - Excavation ongoing. Light bases set. Preparing for sidewalk. Sidewalk being placed. Finishing up irrigation ditches.
    • Foothills Bridge - Diversion wall complete. Backfilling structure. Rail remaining.
    • Dry Creek Bridge - East side complete. Backfilling ongoing. Wall ongoing. Cut off wall remaining.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
  • March 26, 2026

    Share March 26, 2026 on Facebook Share March 26, 2026 on Twitter Share March 26, 2026 on Linkedin Email March 26, 2026 link
    • Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk.
    • Foothills Bridge - Diversion wall complete. Backfilling structure.
    • Dry Creek Bridge - East side complete. Backfilling ongoing. Wall ongoing. Cut off wall remaining.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
    • Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk.
    • Foothills Bridge - Diversion wall complete. Backfilling structure.
    • Dry Creek Bridge - East side complete. Backfilling ongoing. Wall ongoing. Cut off wall remaining.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
  • March 19, 2026

    Share March 19, 2026 on Facebook Share March 19, 2026 on Twitter Share March 19, 2026 on Linkedin Email March 19, 2026 link
    • Linder Road is closed.
    • Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
    • Foothills Bridge - Dewatering setup. Deck placed February 19th. Diversion wall complete. Backfilling structure.
    • Dry Creek Bridge - East side complete. Backfilling ongoing. West side footing placed. Wall ongoing.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
    • Linder Road is closed.
    • Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
    • Foothills Bridge - Dewatering setup. Deck placed February 19th. Diversion wall complete. Backfilling structure.
    • Dry Creek Bridge - East side complete. Backfilling ongoing. West side footing placed. Wall ongoing.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
  • March 13, 2026

    Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 link
    • Speed calming measures have been installed.
    • Linder Road will be closed November 18th through mid-March 2026.
    • Linder Rd o Excavation ongoing. Conduits for lighting ongoing.
    • Foothills Bridge - Dewatering setup. Deck placed February 19th. Diversion wall complete. Backfilling Structure.
    • Dry Creek Bridge - East side complete. Backfilling ongoing. West side footing placed. Wall ongoing.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
    • Speed calming measures have been installed.
    • Linder Road will be closed November 18th through mid-March 2026.
    • Linder Rd o Excavation ongoing. Conduits for lighting ongoing.
    • Foothills Bridge - Dewatering setup. Deck placed February 19th. Diversion wall complete. Backfilling Structure.
    • Dry Creek Bridge - East side complete. Backfilling ongoing. West side footing placed. Wall ongoing.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
  • March 6, 2026

    Share March 6, 2026 on Facebook Share March 6, 2026 on Twitter Share March 6, 2026 on Linkedin Email March 6, 2026 link
    • Speed calming measures have been installed.
    • Linder Road will be closed November 18th through mid-March 2026.
    • Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
    • Foothills Bridge - Dewatering setup. Deck placed February 19th. Diversion wall ongoing. Backfilling Structure.
    • Dry Creek Bridge - East side complete. Shoe fly being installed to allow access to east side. Backfilling ongoing.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
    • Speed calming measures have been installed.
    • Linder Road will be closed November 18th through mid-March 2026.
    • Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
    • Foothills Bridge - Dewatering setup. Deck placed February 19th. Diversion wall ongoing. Backfilling Structure.
    • Dry Creek Bridge - East side complete. Shoe fly being installed to allow access to east side. Backfilling ongoing.
    • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.
Page last updated: 08 May 2026, 11:03 AM