East side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Pole bases and conduits being placed.
- Curb being placed from State Street to Saguaro Dr. - Complete.
- Sidewalk ongoing.
- Bottom lift paving anticipated week of August 10th.
Saquaro Dr to Floating Feather
- Pole Bases being placed.
- Road based ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain being installed.
- Underground power conduit ongoing.
- Development will install sewer line starting August 7th.
- Forming and placing sidewalk once sewer is complete.