August 28, 2026
- East side of Linder Rd
- Sidewalk remaining
- Block wall ongoing
- West side of Linder Rd
- Pole bases and conduits being placed
- Curb being placed from State Street to Saguaro Dr.
- complete
- Sidewalk ongoing
- Bottom lift complete
- Saquaro Dr to Floating Feather
- Pole Bases being placed
- Road based ongoing
- Foothills Bridge
- Rail installed
- Dry Creek Bridge
- Complete
- Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded
- Storm drain installed
- Underground power conduit ongoing
- Development will install Sewer line starting August 7th
- Ongoing
- Forming and placing sidewalk once sewer is complete
Share August 28, 2026 on Facebook
Share August 28, 2026 on X (formerly Twitter)
Share August 28, 2026 on Linkedin
Email August 28, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends