August 7, 2026

  • East side of Linder Rd
    • Sidewalk remaining
    • Block wall ongoing
  • West side of Linder Rd
    • Pole bases and conduits being placed
    • Curb being placed from State Street to Saguaro Dr.
    • Sidewalk ongoing
    • Bottom lift paving anticipated week of August 10th
  • Foothills Bridge
    • Rail remaining
  • Dry Creek Bridge
    • Complete
  • Floating Feather and Linder Roundabout
    • Utilities relocating facilities.
    • Road Subgraded
    • Storm drain being installed
    • Underground power conduit ongoing
    • Development will install Sewer line starting August 7th
    • Forming and placing sidewalk once sewer is complete