August 7, 2026
- East side of Linder Rd
- Sidewalk remaining
- Block wall ongoing
- West side of Linder Rd
- Pole bases and conduits being placed
- Curb being placed from State Street to Saguaro Dr.
- Sidewalk ongoing
- Bottom lift paving anticipated week of August 10th
- Foothills Bridge
- Rail remaining
- Dry Creek Bridge
- Complete
- Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road Subgraded
- Storm drain being installed
- Underground power conduit ongoing
- Development will install Sewer line starting August 7th
- Forming and placing sidewalk once sewer is complete
Share August 7, 2026 on Facebook
Share August 7, 2026 on X (formerly Twitter)
Share August 7, 2026 on Linkedin
Email August 7, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends