December 11, 2025
- Utility work started in advance of construction and is on-going.
- Speed calming measures installed.
- Linder Road will be closed November 18th through mid-March 2026.
Foothills Bridge
- Bridge removed.
- Dewatering setup.
- Excavating for footings.
Dry Creek Bridge
- Precast being fabricated.
Utilities
- Relocating continuing for: Idaho Power, Intermountain Gas and Veolia.