February 19, 2026

  • Speed calming measures have been installed.
  • Linder Road will be closed November 18th through mid-March 2026.
  • Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
  • Foothills Bridge - Dewatering setup. Deck placed February 19th.
  • Dry Creek Bridge - East side complete. Shoe fly being installed to allow access to east side. Starting west side.
  • Utilities - Relocations continuing for: Idaho Power - complete. Intermountain Gas – ongoing. Veolia – ongoing. Fiber utilities - ongoing.