February 5, 2026
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
- Foothills Bridge - Bridge removed. Dewatering setup. Footings placed. South wall placed. Working on north wall. Diversion structure walls placed.
- Dry Creek Bridge- East side complete. Shoe fly being installed to allow access to West side.
- Utilities - Relocations continuing for: Idaho Power - complete. Intermountain Gas – ongoing. Veolia – ongoing. Fiber utilities.