February 5, 2026

  • Speed calming measures have been installed.
  • Linder Road will be closed November 18th through mid-March 2026.
  • Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
  • Foothills Bridge - Bridge removed. Dewatering setup. Footings placed. South wall placed. Working on north wall. Diversion structure walls placed.
  • Dry Creek Bridge- East side complete. Shoe fly being installed to allow access to West side.
  • Utilities - Relocations continuing for: Idaho Power - complete. Intermountain Gas – ongoing. Veolia – ongoing. Fiber utilities.