January 16, 2026

  • Utility work started in advance of construction and is on-going.
  • Speed calming measures have been installed.
  • Linder Road will be closed November 18th through mid-March 2026.

Foothills Bridge

  • Bridge removed.
  • Dewatering setup.
  • Footings placed.

Dry Creek Bridge

  • Precast being fabricated.
  • Starting on east side for installation.

Utilities

Relocating continuing for: Idaho Power, Intermountain Gas, Veolia