January 30, 2026

  • Utility work started in advance of construction and is on-going.
  • Speed calming measures have been installed.
  • Linder Road will be closed November 18th through mid-March 2026.
  • Foothills Bridge: Bridge removed. Dewatering setup. Footings placed. South wall placed. Working on north wall.
  • Dry Creek Bridge: Precast being fabricated. Starting on east side for installation. Headwall being formed.
  • Utilities: Relocations continuing for: Idaho Power - complete. Intermountain Gas, Veolia – ongoing. Fiber utilities.