January 9, 2025
- Utility work started in advance of construction and is on-going.
- Speed calming measures installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Foothills Bridge - Bridge removed. Dewatering setup. Footings placed.
- Dry Creek Bridge - Precast being fabricated. Starting on east side for installation.
- Utilities - Relocation continuing for: Idaho Power, Intermountain Gas & Veolia.