July 9, 2026

East side of Linder Rd

  • Sidewalk remaining.
  • Block wall ongoing.

West side of Linder Rd

  • Excavation and concrete removal.
  • Storm drain ongoing.
  • Pole bases and conduits being placed.

Foothills Bridge - Rail remaining.

Dry Creek Bridge - Complete.

Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading the road.