June 18, 2026

East side of Linder Rd

  • Sidewalk remaining.
  • Block wall construction ongoing.

West side of Linder Rd

  • Excavation and concrete removal.
  • Storm drain installation ongoing.
  • Pole bases and conduits being placed.

Foothills Bridge - Rail installation remaining.

Dry Creek Bridge - Complete.

Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.