March 26, 2026

  • Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk.
  • Foothills Bridge - Diversion wall complete. Backfilling structure.
  • Dry Creek Bridge - East side complete. Backfilling ongoing. Wall ongoing. Cut off wall remaining.
  • Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.