March 26, 2026
- Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk.
- Foothills Bridge - Diversion wall complete. Backfilling structure.
- Dry Creek Bridge - East side complete. Backfilling ongoing. Wall ongoing. Cut off wall remaining.
- Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.