March 6, 2026
- Speed calming measures have been installed.
- Linder Road will be closed November 18th through mid-March 2026.
- Linder Rd - Excavation ongoing. Conduits for lighting ongoing.
- Foothills Bridge - Dewatering setup. Deck placed February 19th. Diversion wall ongoing. Backfilling Structure.
- Dry Creek Bridge - East side complete. Shoe fly being installed to allow access to east side. Backfilling ongoing.
- Utilities: Relocations continuing for: Veolia – up to Briar Rock. Fiber utilities - ongoing.